Litigation Updates & Reports

Updates Between Aug 03, 2023 and Sep 06, 2023

06
Sep
Order 2023 (Interconnection Reforms)

Order 2023 Published in Federal Register; compliance filings, absent further FERC action, due Dec 5, 2023

05
Sep
IEP Parameter Updates

Public Interest Organizations (Sierra Club, CLF) request reh’g of IEP Parameter Updates Order

05
Sep
Brookfield IEP ESF Complaint

Brookfield answers ISO-NE comments and NECOS protest

01
Sep
Membership

FERC accepts involuntary termination of the Participant status of Manchester Methane, eff. Sep 11, 2023

31
Aug
Membership

NEPOOL requests that the FERC accept: (i) the memberships of Phoenix Energy Group and 3Degrees Group; (ii) the termination of the Participant status of: Just Energy (U.S.) Corp., NRG Power Marketing, Norwalk Power, Somerset Power, and WP&G Holdings; and (iii) the name change of NRG Business Marketing, LLC (f/k/a Direct Energy Business Marketing. 

31
Aug
LGIA Termination: ISO-NE/CL&P/NTE CT

FERC accepts notice of termination of  an executed LGIA with NTE Connecticut LLC (“NTE CT”) associated with NTE CT’s proposed Killingly CT combined cycle generating facility

30
Aug
Mystic First CapEx Info. Filing - Settlement Agreement

Mystic submits revised COSA in response to requirements of Aug 1 Mystic First CapEx Info Settlement Order

30
Aug
Versant 2022 MPD OATT Annual Update Settlement Agreement

Versant files an uncontested Joint Offer of Settlement between itself and the Maine Wholesale Customer Group, the Aroostook Energy Association, the Maine Office of the Public Advocate, and the Maine Public Utilities Commission (together, the Maine Parties) which, if approved, would resolve all issues raised by the Maine Parties with regards to Versant’s 2022 annual update to the transmission charges under the MPD OATT.

29
Aug
Sched. 21-VP: 2022 Annual Update Settlement Agreement

Versant Power files Settlement Agreement to resolve all issues raised by the MPUC following Versant’s 2022 BHD Annual Update filing;
comment deadline Sep 19, 2023

29
Aug
Schedule 21-VP: Versant/Black Bear LSAs

Versant submits Refund Report detailing the time value refunds it paid to Black Bear Hydro Partners, LLC and Black Bear SO, LLC on Aug 18, 2023, in response to order accepting the Local Service Agreements eff. Aug 1, 2023, rather than Jan 1, 2023. 

28
Aug
Second New England Gas-Electric Forum

EMM submits comments

28
Aug
Att. F App. D Depreciation Rate Change (CMP)

FERC accepts CMP’s proposed updated depreciation rates for its transmission facilities that are set forth in Appendix D to Attachment F of the ISO-NE OATT, eff. Jul 1, 2023

28
Aug
Order 2023 (Interconnection Reforms)
RM22-14
28
Aug
Membership

FERC accepts (i) Hecate Energy Albany 2, Erie Wind and SCEF1 FUEL CELL memberships; (ii) termination o the Participant status of: Concurrent, and Brookfield Energy Marketing LP; and the name change of CPV Spruce Mountain Wind, LLC (f/k/a Spruce Mountain Wind, LLC)

28
Aug
Order 2222 Compliance Filing Order - 180-Day Compliance Filing

ISO-NE submits 180-day compliance filing, comments due Sep 18, 2023

28
Aug
CSC CIP-IROL (Schedule 17) Section 205 Cost Recovery Filing

FERC accepts revised CSC rate schedule that allows for recovery of $723,601 in CIP-IROL Costs incurred between Jun 1, 2021 and Dec 31, 2022. 

22
Aug
Brookfield IEP ESF Complaint
EL23-89

Comments and protests to Brookfield’s Complaint filed by ISO-NE, FirstLight, NECOS, and NEPGA

22
Aug
CIP IROL (Schedule 17) Section 205 Cost Recovery Filing: Bucksport Generation

Bucksport amends its filing to remove working capital and interest on operations and maintenance costs from its cost recovery filing.

22
Aug
CIP IROL (Schedule 17) Section 205 Cost Recovery Filing: Stonepeake Kestral

Stonepeak Kestrel amends its filing to remove working capital and interest on operations and maintenance costs from its cost recovery filing.

22
Aug
FCA18 De-List Bids Filing

FERC accepts ISO-NE’s filing describing the Permanent and Retirement De-List Bids received in connection with FCA18, eff. Sep 11, 2023

21
Aug
ISO-NE FERC Form 3Q

ISO-NE submits its 2023 Q2 FERC Form 3Q

17
Aug
D&E Agreement Amendment: PSNH / NECEC

PSNH files amendment to D&E Agreement with NECEC to change the scope of the Services provided to include certain procurement activities and to correspondingly reflect an increase in Payment Security.

16
Aug
Capital Projects Report - 2023 Q2

NEPOOL submits comments supporting ISO-NE’s 2023 Q2 Capital Projects Report.

15
Aug
Mystic Second CapEx Info. Filing

NESCOE, as it had agreed to in the FERC-approved First CapEx Settlement Agreement, submits a notice of withdrawal of its October 17, 2022 Formal Challenge No. III.A to the 2022 Informational Filing (its challenge that the 2023 CapEx Projects were unsupported).

15
Aug
Engineering & Test Agreement: CL&P/BPUS

FERC accepts Engineering and Test Agreement, eff. Jul 6, 2023

14
Aug
PURPA Enforcement Petition: Allco Finance Limited
EL23-84

NECEC Transmission and Maine Office of Public Advocate protest Allco PURPA Complaint; MA State Agencies request extension of time, to Oct 23, 2023, to file its response to the Complaint

14
Aug
Interconnection Study Metrics Processing Time Exceedance Report 2023 Q2

ISO-NE files its Interconnection Study Processing Metrics Time Exceedance Report for 
the second quarter of 2023

14
Aug
Order 881 Further 60-Day Compliance Filing

ISO-NE, NEPOOL, PTO AC, and CSC file changes in response to the New England Order 881 Compliance Order.

11
Aug
Capital Projects Report - 2023 Q2

ISO-NE files 2023 Q2 Report.

11
Aug
FAP Eligible LOC Issuer Changes

FERC accepts changes, eff. Aug 27, 2023 

11
Aug
Schedule 21-VP Real Power Loss Factor Change

FERC accepts changes, eff. Sep 1, 2023

10
Aug
IA Cancellation: NEP/TransCanada

FERC accepts, eff. Aug 14, 2023, NEP’s notice of cancellation of its Interconnection Agreement with TransCanada Hydro Northeast Inc. (TransCanada) that has been superseded by a new SGIA between NEP and Great River Hydro, TransCanada’s successor in interest.

09
Aug
Sched 21-VP: Real Power Loss Factor Change

Versant supplements its filing with a “Study of Transmission and Distribution Losses by Rate Group in Versant Power Service Area”, inadvertently not included as an Exhibit to its Jun 15, 2023 filing.

08
Aug
Versant Power Att. F App. D Depreciation Rate Change

Versant supplements its Jul 26, 2023 filing with the following: Qualification Statement (Exhibit JFW-1); Maine Public Rate District Depreciation Study (Exhibit JFW-3); Comparison of Current Annual Depreciation Expense vs. Proposed Annual
Depreciation Expense for BHD (Exhibit JFW-4); and Comparison of Current Annual Depreciation Expense vs. Proposed Annual Depreciation Expense for MPD (Exhibit JFW-5).

04
Aug
IEP Parameter Updates

FERC accepts IEP Parameter Updates, without change or condition, effective Aug 4, 2023