Litigation Updates & Reports

Updates Between Aug 01, 2024 and Sep 03, 2024

03
Sep
Versant Order 1920 MPD Waiver Request

FERC grants Versant Power’s waiver request of the regional transmission planning, interregional transmission coordination, and cost allocation requirements of Order 1920 for the MPD

03
Sep
FERC Workshop: Innovations & Efficiencies in Generator Interconnection

FERC issues 3rd supplemental notice of Sep 10-11, 2024 workshop

30
Aug
Membership

New Members: Elyctra LLC and Halia Energy LLC; and Termination of Participant status: Town on Hanover, New Hampshire

30
Aug
206 Proceeding: TO Initial Funding Show Cause Order

Parties appeal FERC orders in 8th Circuit

30
Aug
ISA: PSNH / Wok, LLC

NFERC accepts ISA, eff. Jul 16, 2024

29
Aug
GDQ ESS Waiver Request: Late Stage SIS Process

GDQ ESS requests waiver of pending Tariff provisions so as to allow its acceptance after Aug 30, 2024 of the SIS results for its facility to enable its LGIA to benefit from the proposed Late-Stage SIS Process and for it to be refunded its deposits associated with participation in the Transitional Cluster Study; comment deadline Sep 19, 2024

28
Aug
203 Application: Trailstone / Engelhart

Trailstone Companies file notice of consummation of transaction making Trailstone Companies and Engelhart US Related Persons

27
Aug
DASI Conforming Changes

ISO-NE and NEPOOL jointly file Tariff revisions to supplement the core DASI Rules, and address the impacts of the core DASI design on a number of secondary market-related processes; comment deadline Sep 15, 2024

26
Aug
Transmission Rate Annual (2023-24) Update/Informational Filing

New England Power and Narragansett submit, in response to the FERC’s July 26 letter, their public responses to the MOPA’s September 15 Information Requests

23
Aug
ISO-NE FERC Form 3Q

ISO-NE submits its 2024 Q2 FERC Form 3Q

23
Aug
Transmission Rate Annual (2023-24) Update/Informational Filing
ER20-2054-000

Eversource and MEPCO submit their responses to the FERC’s July 26 letter requesting copies of their public responses to the MOPA’s September 15 Information Requests

23
Aug
2025 NERC Budget Filing

NERC submits proposed 2025 Business Plan and Budget for itself and its Regional Entities, including NPCC; comment deadline Sep 13, 2024

23
Aug
203 Application: Carlyle Group (Nautilus) / Q-Generation (Trafigura)

Applicants request authorization for Q-Generation’s acquisition of 100% of the interests of a company indirectly owned by investment fund vehicles managed/advised by The Carlyle Group (owner of Nautilus Power and its Related Persons); comment deadline Sep 13, 2024

23
Aug
CRA Cancellation: NEP/Holden

NEP files notice of cancellation of its Cost Reimbursement Agreement with Holden; comment deadline Sep 13, 2024

22
Aug
Membership

FERC accepts Aurora Energy Research and Enverus as new members and the termination of Participant status of KCE CT 10, LLC

21
Aug
Waiver Request: Withdrawal from IEP and Return of IEP Net Revenues Received) (Canal Marketing/Canal 3)

Chief Judge designates ALJ Patricia Hurt as the Settlement Judge in this proceeding; first Status Report due Sep 20, 2024

21
Aug
LCCSA: RIE/BIPCO/Pascoag

FERC accepts RI Energy’s Local Control Center Services Agreement with BIPCO and Pascoag, eff. May 30, 2024

16
Aug
National Grid ESS Wholesale Distribution Tariffs
ER24-2796; ER24-2795

Massachusetts Electric Co. and Nantucket Electric Co. file new Wholesale Distribution Tariffs to provide for National Grid’s recovery of costs associated with the provision of Wholesale Distribution Service (“WDS”) to customers who own qualifying standalone electric energy storage systems (“ESS”) connected to National Grid’s distribution system and who charge those  resources via deliveries over National Grid’s distribution system for purposes of making wholesale sales through the wholesale ISO-NE markets.

16
Aug
D&E Agreement: CL&P / BPUS Generation Development

FERC accepts termination of D&E Agreement, eff. Jun 26, 2024

16
Aug
FERC Tech Conf: Large Loads Co-Located at Generating Facilities

FERC issues supplemental notice of Nov 1, 2024 tech. conf.

15
Aug
Capital Projects Report - 2024 Q2

NEPOOL files comments supporting ISO-NE 2024 Q2 Report

15
Aug
206 Proceeding: TO Initial Funding Show Cause Order

FERC issues Allegheny Notice noting that Indicated Utilities’ request for reh’g may be deemed to have been denied by operation of law, but noting that Indicated Utilities’ request will be addressed in a future order

14
Aug
Interconnection Study Metrics Processing Time Exceedance Report 2024 Q2

ISO-NE files required quarterly report

14
Aug
MW-Dependent Fuel Price Adjustments
ER24-2584

IMM, Vistra, NEPGA, file comments supporting changes

14
Aug
Mystic COSA ROE Settlement

Constellation Mystic Power, LLC (“Mystic”) requests approval of an uncontested Settlement Agreement establishing a settled Return on Equity (“ROE”) that would, if approved, moot all ROE  appeals currently pending before the DC Circuit related to the ROE in the Mystic COS Agreement.  The Settlement Agreement establishes an ROE of 9.0% for the entirety of the Term (“Settled Mystic ROE”), a reduction from the currently-on-file ROE of 9.19%.  Comment deadline Sep 4, 2024.

14
Aug
FERC Workshop: Innovations & Efficiencies in Generator Interconnection

FERC issues 2nd supplemental notice of Sep 10-11, 2024 workshop

13
Aug
Fitchburg Att. F App. D Depreciation Rate Changes

FG&E proposes updated depreciation rates in its Regional and Local Service formula rate calculations, which will result in an estimated annual decrease of $28,067 to depreciation expense and have a de minimus effect on the transmission rates of Regional and Local Service customers.

12
Aug
Waiver Request: Withdrawal from IEP and Return of IEP Net Revenues Received) (Canal Marketing/Canal 3)

FERC establishes settlement judge procedures to address the issue of whether and how Canal Marketing should return revenues or net revenues, with applicable interest, to ISO-NE.

12
Aug
Order 2222 Compliance Filing

NEPOOL files comments supporting ATTR Submetering Revisions

12
Aug
Mystic COSA Protocols Waiver Request

FERC grants waiver of the deadlines in Sections II.6.A and II.4.F of the COSA Protocols so that the deadline to make the 2024 Informational Filing (and subsequent related deadlines) can be delayed to allow Mystic and active intervenors in ER18-1639-027, who have agreed to a settlement in principle in that proceeding, to determine whether a settlement can be reached that may impact or obviate the need for the filing or challenges that might be filed subsequent thereto.

12
Aug
Joint Federal-State Current Issues Collaborative

FERC issues order listing the state commission members of the Federal and State Current Issues Collaborative: from NECPUC: MPUC Chairman Phil Bartlett and NHPUC Commissioner Pradip Chattopadhyay; from MACRUC: PA PUC Vice Chair Kimberly M. Barrow and PH PUC Commissioner Dennis P. Deters; from the Mid-America Regulatory Conference: IN Utility Regulatory Commission Chairman Jim Huston and MI PUC Commissioner Katherine Peretick; from SEARUC: NC Utilities Commissioner Kimberly W. Duffley and FL PSC Commissioner Art Graham; and from WESTERN: ID PUC Commissioner Eric Anderson and NM Public Regulation Commission Chair Patrick O’Connell.

09
Aug
RENEW Network Upgrades & O&M Cost Allocation Complaint

RENEW answers TOs Jul 31 Answer

09
Aug
LGIA - ISO-NE / CL&P / Brookfield Husky Solar

ISO-NE files for acceptance a non-conforming LGIA covering the interconnection of Brookfield’s ~50 MW solar facility located in Sterling, CT (non-conforming only in that it is unexecuted).  ISO-NE states that FERC acceptance of the LGIA will eliminate any uncertainty remaining regarding the issue of whether Sterling Property, LLC retains any right to use the 87 MW of capacity on the CL&P Tie Line pursuant to the IA between Sterling and CL&P.

09
Aug
Capital Projects Report - 2024 Q2

ISO-NE files Q2 2024 Capital Projects Report

08
Aug
D&E Agreement: CL&P / BPUS Generation Development

FERC accepts Agreement, eff. Aug 11, 2024

07
Aug
Order 2023 Compliance & Related Changes

ISO-NE files answer to Longroad’s Aug 5, 2024 answer 

07
Aug
Mystic Second CapEx Info. Filing Settlement Judge Proceedings

Judge French submits 4th status report recommending continuation of settlement proceedings

05
Aug
eTariff § I.2.2 Conforming Changes

FERC accepts changes, eff. Apr 15, 2024

05
Aug
Order 2023 Compliance & Related Changes

Longroad Energy answers ISO-NE’s Jul 19 Answer

05
Aug
D&E Agreement: CL&P / Vineyard Northeast

CL&P withdraws filing (D&E Agreement terminated without any services being provided thereunder)

05
Aug
CMP ESF Service Rate

Judge Hessler issues 2nd status report recommending continuation of settlement judge procedures

02
Aug
D&E Agreement Cancellation NSTAR/Hingham

NSTAR submits notice of cancellation of D&E Agreement; comment deadline Aug 23, 2024

02
Aug
Bear Swamp Power Co. CIP IROL (Schedule 17) Cost Recovery Schedule Filing

FERC accepts rate schedule that allows Bear Swamp to begin the recovery period for certain CIP-IROL Costs under Schedule 17 of the ISO-NE Tariff

02
Aug
Bear Swamp Power Co. CIP IROL (Schedule 17) Cost Recovery Schedule Filing

FERC accepts Bear Swamp Power Co.’s CIP-IROL Rate Schedule, eff. Jun 12, 2024