Litigation Updates & Reports

Updates Between Oct 05, 2022 and Nov 01, 2022

28
Oct
203 Application: ConEd / RWE

ConEd and RWE request authorization for a transaction pursuant to which RWE will acquire 100% of the equity interests in ConEd’s Clean Energy Businesses

28
Oct
203 Application: Great River Hydro / HQI US

Great River Hydro and HQI US request authorization for a transaction pursuant to which HQI US will indirectly acquire 100% of the membership interests in Great River Hydro

26
Oct
FTR Collateral Show Cause Order

ISO-NE answers in response to Jul 28, 2022 Show Cause Order.  ISO-NE suggests that the FERC should find that the ISO’s existing FAP FTR
financial assurance calculations are just and reasonable; to the extent it does not, ISO-NE suggests that it should be allowed to follow the established stakeholder  process to propose revisions to the FAP to incorporate an FTR volumetric minimum financial assurance requirement.

26
Oct
Order 864 Compliance Filings - CMP

FERC accepts CMP’s LNS and Schedule 1 Appendix A Implem. Rule Order 864 compliance filings.

26
Oct
TOs' Attachment F Depreciation Normalization Requirements Revisions

TOs submit revisions to Attachment F to Section II of the Tariff to apply the IRS’s ADIT proration formula to their actual (true-up) revenue requirements.  The revisions are intended to maintain compliance with the IRS’s depreciation normalization requirements and to ensure their continued ability to use accelerated depreciation.  In an April 1, 2022 IRS Private Letter Ruling (“PLR”), the IRS held that the IRS’s depreciation normalization rules require the application of the ADIT proration formula in the actual (true-up) revenue requirement if the IRS’s proration formula was required to be applied in the calculation of the forecasted transmission revenue requirement.  The proposed Revisions are intended to be consistent with the PLR.

26
Oct
Order 864 Compliance Filing - NEP (Schedule 21-NEP and TSA-NEP-22)

FERC accepts NEP’s Order 864 Schedule 21-NEP and TSA-NEP-22 Compliance Revisions, eff. Jan 27, 2020, and Jan 1, 2022

25
Oct
Schedule 21-RIE

RI DPUC submits comments expressing concern that the record in the proceeding is not adequate to demonstrate the justness and reasonableness of RIE’s filing; requests that REI provide additional information 

25
Oct
Order 864 Compliance Filing - NEP (Tariff No. 1)

FERC accepts NEP (Tariff No. 1) Order 864 compliance changes, eff. Jan 27, 2020 and Jan 1, 2022, as requested

25
Oct
Order 864 Compliance Filing - NEP (MECO/Nantucket LSA)

FERC accepts NEP’s MECO/Nantucket LSA Order 864 compliance filing, effective Jan 27, 2020 and Jan 1, 2022, as requested

24
Oct
Schedule 21-NEP Changes (Removal of References to Narragansett; Updated References to National Grid LCC)

National Grid files changes to Schedule 21-NEP to remove references to Narragansett and update references to National Grid’s local control center

24
Oct
E&P Agreement: NextEra Energy Seabrook/NECEC

FERC accepts E&P Agreement , eff. Sep 8, 2022

20
Oct
FERC 2022-23 Winter Energy Market and Reliability Assessment

Staff issues Report to the FERC regarding Staff’s 2022-2023 Winter Energy Market and Reliability Assessment 

19
Oct
IA Cancellation: New England Power / Pawtucket

New England Power submits Notice of Cancellation of the Firm Local Generation Deliverability Service Agreement with Pawtucket Power Associates Limited Partnership

18
Oct
Schedule 21-NEP: Narragansett/ Pawtucket Power Decomm. CRA

FERC accepts a Decommissioning Cost Reimbursement Agreement (CRA) between Narragansett Electric and Pawtucket Power Associates LP (Pawtucket), eff. Jul 26, 2022.  The Decommissioning CRA facilitates the performance of certain work that Pawtucket has requested Narragansett undertake to support the decommissioning of certain interconnection facilities and related equipment for Pawtucket’s 69 MW Rhode Island generating facility that was completely retired on Jun 1, 2022. 

17
Oct
ENECOS Mystic COSA Complaint

Eastern New England Consumer-Owned Systems submit Complaint against Mystic and ISO-NE challenging the unjust and unreasonable pass-through to ISO-NE
customers of firm pipeline transportation costs under the 2nd Amended and Restated Cost-of-Service Agreement (COSA), which ENECOs claim are associated
with pipeline facilities that are neither used nor usable to supply fuel to Mystic 8 and 9, and therefore should not be charged to ISO-NE and its customers
under the COSA.  ENECOS ask that all references to “Pipeline Transportation Agreements” be stricken from the COSA, remove from the true-up methodology template Line No. 7 “Fixed Pipeline Transportation,” and preclude Mystic from recovering the dollar amounts associated with that line item.

17
Oct
Mystic 2022 Capital Expenditures Info Filing
ER18-2639

ENECOS and NESCOE submit formal challenges to Mystic’s 2022 Capital Expenditures Informational Filing

17
Oct
Modernizing Electricity Market Design - Resource Adequacy

ISO-NE files files 94-page report in response to the FERC’s Apr 21, 2022 Order Directing Reports

14
Oct
2023 NESCOE Budget

ISO-NE files materials for funding NESCOE’s 2023 operations

14
Oct
2023 ISO-NE Administrative Costs and Capital Budgets

ISO-NE files its 2023 administrative costs and capital budgets

14
Oct
LFTR Implementation Quarterly Status Reports

ISO-NE files its 56th quarterly report

14
Oct
Capital Projects Report - 2022 Q3

ISO-NE files 2022 Q3 Report

13
Oct
Interconnection Reforms NOPR

NEPOOL submits initial comments in response to Interconnection Reforms NOPR

13
Oct
E&P Agreement Termination: CL&P / EIP Investment

CL&P files notice of termination of E&P Agreement with EIP Investment (which has since signed an LGIA with CL&P and ISO-NE)

12
Oct
FCM Parameters Recalculation Schedule Modification

ISO-NE and NEPOOL file changes to defer and modify the FCM Parameters Recalculation Schedule

11
Oct
Schedule 21-RIE

National Grid submits comments supporting the Schedule 21- REI filing

11
Oct
FCA18 Schedule Modifications

ISO-NE and NEPOOL submit revisions to the Tariff to modify the schedule for the eighteenth Forward Capacity Auction (FCA18) only

07
Oct
Order 864 Compliance Filing - TOs RNS Compliance Filings

FERC accepts New England TOs pending Order 864 (RNS) compliance filings

07
Oct
NOPR: ISO/RTO Credit Information Sharing

NEPOOL submits comments on ISO/RTO Credit Information Sharing NOPR

05
Oct
Order 864 Compliance Filings -NEP (Schedule 21-NEP and TSA-NEP-22 Compliance Revisions)
ER20-2251 / ER20-2553

NEP submits supplemental information in support of its July 18 NEP (Schedule 21-NEP and TSA-NEP-22 Compliance Revisions) and NEP (MECO/Narragansett LSA) compliance filings

2024 Reports

2015 Reports

Close