Litigation Updates & Reports

Updates Between Apr 06, 2023 and May 03, 2023

28
Apr
LGIA 2nd Rev: REI / Manchester Street / ISO-NE

ISO-NE, Rhode Island Energy and Manchester Street file 2nd revised LGIA to revise the LGIA in its entirety to reflect RIE as the new Interconnecting Transmission Owner and associated contacts

28
Apr
IEP Parameter Updates
ER23-1588

Comments and protests on IEP Parameter Updates filed by: Consumer Advocates, Indicated Suppliers, Sierra Club

28
Apr
Updated RI Genco LGIA and SGIA

ISO-NE, Rhode Island Energy and RI Genco file 2nd revised LGIA and 1st Rev SGIA to reflect RIE as the new Interconnecting Transmission Owner and associated contacts

28
Apr
VEC Annual Transmission Formula Rate Informational Filing

VEC files its 20th annual rate update containing the calculations and associated workpapers for its transmission charges under Local Service Schedule 20A-VEC
and 21-VEC, effective for the July 1, 2023 to June 30, 2024 period  

28
Apr
LGIA 1st Rev: REI / Ocean State / ISO-NE

ISO-NE, Rhode Island Energy and Ocean State file 1st revised LGIA to reflect RIE as the new Interconnecting Transmission Owner

28
Apr
Membership

NEPOOL requests that the FERC accept: (i) the memberships of Carbon Solutions Group (GIS-Only Participant); PPL TransLink Inc. [Related Person to Rhode Island Energy (Transmission Sector)]; and Second Foundation US Trading, LLC (Supplier Sector); (ii) the termination of the Participant status of EnPowered USA LLC; Invenia Technical Computing Corp.; Uniper Global Commodities NA LLC; and WATTIFI INC.; and (iii) the name changes of RWE Clean Energy Wholesale Services, Inc. (f/k/a Consolidated Edison Energy, Inc.); RWE Clean Energy Asset Holdings, Inc. (f/k/a Consolidated Edison Development, Inc.); RWE Clean Energy Solutions, Inc. (f/k/a Consolidated Edison Solutions, Inc.); and SYSO Inc. (f/k/a SYSO LLC)

28
Apr
New England Gas-Electric Winter Forum II

FERC issues errata notice identifying correct address for Second Forum (DoubleTree by Hilton Portland, 363 Maine Mall Rd, Portland, ME, 04106) and additional instructions for panelist/speaker self-nominations

27
Apr
Mystic Complaint Order Compliance Filing

Mystic files revised COS Agreement in response to directives in the Complaint Order

27
Apr
CNRIS Time-Out Rules Removal
ER23-1581

AEU and RENEW file comments supporting the removal of Capacity Network Resource Interconnection Service (CNRIS) time-out rules from Section 4.4 of Schedules 22 and 25 and from Section 1.5.5 of Schedule 23 for Queue Positions that have not timed-out (in whole or part) by FCA 17

27
Apr
Mystic I Order on Remand

Mystic requests rehearing of Mystic I Order on Remand

27
Apr
Mystic I Order on Remand

Mystic submits compliance filing in response to requirements of Mystic I Order on Remand

27
Apr
Membership

FERC accepts (i) the membership of Calpine Community Energy [Related Person to Calpine Energy Services et al. (Generation Sector)]; (ii) the termination of the Participant status of Clean Choice Energy (Supplier Sector); InBalance, Inc. (Supplier Sector); and Stored Solar J&WE, LLC (AR Sector, RG Sub-Sector); and (iii) the name change of Interstate Gas Supply, LLC (f/k/a Interstate Gas Supply, Inc.)

24
Apr
RTO/ISO Common Performance Metrics

ISO-NE files FERC Form-922 (RTO/ISO Common Performance Metrics) for 2019-2022

24
Apr
IEP Remand Compliance Changes Order

FERC accepts ISO-NE’s compliance filing, eff. May 28, 2019 (alternative Tariff changes proposed by Brookfield that would have explicitly allowed pumped hydro resources to participate in the IEP as Electric Storage Facilities were rejected on procedural grounds).

21
Apr
Membership - NTE CT Involuntary Termination

NEPOOL and ISO-NE request the involuntary termination of the Participant status of NTE Connecticut, LLC

20
Apr
SGIA - NEP/Great River Hydro

FERC accepts SGIA, eff. Jan 30, 2023

20
Apr
D&E Agreement Amendment: NSTAR / Vineyard Wind

NSTAR files 1st amendment to Vineyard Wind D&E Agreement to extend the term of the Agreement for additional work and amending the scope of work of the Agreement to (i) address the risks and impacts to milestone revisions; (ii) to address the impact of higher rating of certain Direct Assigned Facilities; and (iii) to conduct harmonic study and data collection

20
Apr
ISO-NE 2022 FERC Form 582 Reporting Requirement

ISO-NE submits 2022 annual report of total MWh of transmission service (approx. 125 million MWhs) (roughly 1.1 million MWh more than 2021)

17
Apr
Order 2222 Compliance Filing Order

Advanced Energy United answers Mar 31 ISO-NE Request for Rehearing  

17
Apr
203 Application: Energy Harbor / Vistra

Energy Harbor and Vistra request approval for a proposed transaction pursuant to which Energy Harbor and the Vistra Public
Utilities will become indirectly owned by a newly-formed subsidiary holding company of Vistra — “Vistra Vision” 

14
Apr
LFTR Implementation Quarterly Status Reports

ISO-NE files its 58th quarterly report

14
Apr
Mystic First CapEx Info. Filing - Settlement Agreement

State Settling Parties submit reply comments in response to ENECOS’ initial comments 

14
Apr
Schedule 21-NEP: NEP/Dichotomy Collins Hydro SGIA

National Grid submits response to deficiency letter

14
Apr
Membership Suspension Notice - Rivercrest Power-SOUTH

ISO-NE files notice of Apr 12 suspension of Rivercrest Power-SOUTH, LLC from the New England Markets

14
Apr
ISO-NE 2022 FERC Form 1

ISO-NE submits its 2022 FERC Form 1

14
Apr
Transmission Rate Annual (2022-23) Update/Informational Filing

Eversource answers RENEW’s Mar 31 answer

14
Apr
Dynegy Add’l Cost Recovery Due to Dec 24 General Threshold Energy Mitigation

Dynegy answers April 4 protests by MOPA and MA AG/CT OCC

14
Apr
Order 2222 Compliance Filing Order

MA AG answers National Grid’s Mar 31 request for rehearing

13
Apr
Second New England Gas-Electric Forum

FERC issues supplemental notice of the Second New England Gas-Electric Forum to be held June 20, 2023 in Portland, ME 

11
Apr
D&E Agreement: NSTAR / Commonwealth Wind

NSTAR files D&E Agreement

11
Apr
RFA Cancellation - NSTAR / Ocean State Power

NSTAR files to terminate Related Facilities Agreement with Ocean State Wind, having determined that pursuant to capital project upgrades on its own system for its
own purposes, the Related Facilities were no longer necessary.

11
Apr
Order 2222 Compliance Filing Order - 60-Day Compliance Filing

FERC extends 60-day compliance deadline by 8 days, to May 9, 2023

06
Apr
Seabrook Complaint and Seabrook Declaratory Order Petition

NextEra Energy Resources and NextEra Energy Seabrook file copy of appeal to DC Circuit of the FERC’s Seabrook Dispute Order and Seabrook Dispute Allegheny Order

06
Apr
NCRIS Time-Out Rules Removal

ISO-NE, NEPOOL and PTO AC file revisions to the OATT that remove the Capacity Network Resource Interconnection Service (CNRIS) time-out rules from Section  4.4 of Schedules 22 and 25 and from Section 1.5.5 of Schedule 23 for Queue Positions that have not timed-out (in whole or part) by FCA17