Litigation Updates & Reports

Updates Between May 04, 2022 and Jun 17, 2022

06
Jun
IA: NEP / Narragansett

New England Power Company (NEP) and Narragansett Electric Company file wires-to-wires interconnection agreement to govern the interconnection of the two companies transmission systems

03
Jun
Attachment F Corrections & Updates

PTO AC submits proposed revisions to Attachment F of the OATT to (i) correct minor errors in certain worksheets of the “Formula Rate Template” contained in Appendices A and B; and
(ii) update the name of Versant Power in Appendices A, B and D.

01
Jun
ISO-NE 2021 FERC Form 714

ISO-NE submits its Annual Electric Balancing Authority Area and Planning Area Report for calendar year 2021. Through its Form 714 filing, ISO-NE reports, among other things, generation in the New England Control Area, actual and scheduled inter-balancing authority area power transfers, and net energy for load, summer-winter generation peaks and system lambda.

01
Jun
203 Application: Stonepeak / JERA Americas

Stonepeak and its Related Person public utilities request authorization for the sale of 100% of their membership interests to a wholly-owned subsidiary of JERA Americas Inc.

31
May
CL&P Att. F App. D Depreciation Rate Change

FERC accepts CL&P’s proposed changes to the transmission plant depreciation rate for the Norwalk  Harbor-Northport underground transmission line set forth in CL&P’s Appendix D to Attachment F of the ISO-NE OATT

31
May
Membership

NEPOOL requests that the FERC accept (i) the following Applicant’s membership in NEPOOL:  Ebsen LLC and Umber (Supplier Sector); (ii) the termination of the Participant status of Dantzig Energy; Pilot Power Group; and Twin Eagle Resource Management; and (iii) the name change of LS Power Grid Northeast, LLC (f/k/a New England Energy Connection, LLC)  

31
May
FCA16 Results Filing

No Coal No Gas answers ISO-NE’s May 16, 2022 answer

27
May
MOPR Elimination Filing

FERC accepts, without change or condition, ISO-NE’s and NEPOOL’s proposal to eliminate MOPR following the implementation of a two-year transition mechanism and to replace it with a reformed buyer-side market power mitigation review construct.  The transition mechanism revisions were accepted eff. May 30, 2022; the reformed mitigation construct revisions, Mar 1, 2024, as requested.  The order includes separate concurrences by Chairman Glick, Commissioner Christie, Commissioners Clements and Phillips, and a dissent by Commissioner Danly.

27
May
ISO-NE FERC Form 3Q

ISO-NE submits its 2021 Q4 FERC Form 3Q

26
May
Membership

FERC accepts the NEPOOL memberships of: AMP Solar US Holdings, Power Kiosk and Octopus Energy 

26
May
IMM 2021 Annual Markets Report

IMM files annual report covering calendar year 2021

25
May
Office of Public Participation - No Coal No Gas FCA16/Merrimack Station Comments

Comments by No Coal No Gas sent to the FERC’s Office of Public Participation 

25
May
Transmission NOPR

FERC extends the Transmission NOPR initial comment and reply comment deadline to Aug 17, 2022 and Sep 19, 2022, respectively

20
May
Schedule 21-NEP: Revised RI LSAs Compliance FIling

New England Power submits a compliance filing to (1) reflect all changes to the LSAs accepted by the FERC in ER22-707 and ER22-927 and (2) provide executed versions of the conformed LSAs

20
May
MOPR Elimination Filing

North East Offshore submits limited answer (to clarify its views on the MOPR Elimination Filing)

20
May
Capital Projects Report - 2022 Q1

NEPOOL submits comments on ISO-NE’s 2022 Q1 Capital Projects Report filing

20
May
Membership Suspension Notice - Pilot Power Group

ISO-NE files notice of May 18 suspension of Pilot Power Group  from the New England Markets

19
May
New England Gas-Electric Winter Forum

FERC announces a Sep 8, 2022 forum, to be held in Burlington, VT, to discuss the electricity and natural gas challenges facing the New England Region.  The objective of the forum is to achieve greater understanding among stakeholders in defining the electric and natural gas system challenges in the New England Region.    

19
May
Order 881: Managing Transmission Line Ratings

FERC issues order addressing arguments raised on rehearing and clarification 

18
May
Order 2222 Compliance Filing

FERC issues 25-page Deficiency Letter requiring ISO-NE to file additional information as an amendment to its 2/2/22 filing; deficiency letter response due on or before Friday, Jun 17, 2022

17
May
MOPR Elimination Filing

Clean Energy and Consumer Advocates answer ISO-NE, NEPOOL, NEPGA, and Calpine/Cogentrix/Vistra answers

17
May
RENEW/ACPA Resource Capacity Accreditation & Operating Reserve Designation Complaint

ISO-NE answers RENEW/ACPA Apr 29 answer

16
May
Interconnection Study Metrics Processing Time Exceedance Report Q1 2022

ISO-NE files required quarterly report for Q1 2022 

16
May
203 Application: Pixelle / Spectrum

FERC authorizes the sale of 100% of the interests in Pixelle Holding by affiliates of the LG Fund to Spectrum Group Buyer

16
May
Order 2222 Compliance Filing
ER22-983
16
May
FCA16 Results Filing

ISO-NE answers comments by SEIA and NTE CT, and protests submitted by several individuals

12
May
LGIA: CL&P / EIP Investment

CL&P files non-conforming LGIA with EIP Investment to govern the interconnection of EIP’s 20 MW fuel cell project through Interconnection Facilities that include facilities owned and used by The Farmington River Power Company to serve the Stanley Black & Decker manufacturer campus in New Britain, Connecticut

12
May
Capital Projects Report - 2022 Q1

ISO-NE files 2022 Q1 Report

11
May
MOPR Elimination Filing

ISO-NE answers protests filed in this proceeding

10
May
IA Termination: CL&P/Sterling Property

Eversource answers Sterling’s request for clarification and/or rehearing of the Sterling IA Allegheny Order 

10
May
Order 864 Compliance Filing - UI

UI submits further Order 864 compliance filing changes, with changes to Schedule 21-UI including revisions to its rate base adjustment mechanism, Attachment D amortization of excess or deficient ADIT, and a new permanent worksheet (Attachment M) that will be used to annually track information related to excess or deficient ADIT

06
May
MOPR Elimination Filing
ER22-1528

NEPOOL, NEPGA file answers to protests

05
May
FCA16 Results Filing
ER22-1417

Comments filed by: NTE Connecticut, SEIA

05
May
MOPR Elimination Filing

Calpine/Cogentrix/Vistra jointly answer pleadings filed by: Clean Energy & Consumer Advocates; MA AG/MOPA; MA Exec. Office of Energy and Environ. Affairs

04
May
IMM Quarterly Markets Reports - 2022 Winter

IMM files Winter 2022 Report; to be reviewed at the May 10 Markets Committee meeting

2015 Reports

Close