Litigation Updates & Reports

Updates Between Nov 06, 2025 and Dec 03, 2025

02
Dec
Waiver Request: Capacity Performance Payment Calculation and Use of Late Payment Account (ISO-NE)

FERC grants Calpine Solutions’ request for waiver of the requirement to submit Meter Data Error RBA using the form posted on the ISO’s website.  The information was timely provided via AskISO and provided on the required form one day after the Submission Limit deadline. 

28
Nov
Membership

FERC accepts (i) the memberships AE-ESS Holyoke, LLC; American Power & Gas of RI, LLC; and Burgess BioPower; and (ii) the termination of the Participant status of Hudson Energy Services

26
Nov
Membership

New Member: The Energy Authority; Name Changes: Long Island Power Authority (f/k/a Long Island Lighting Company d/b/a LIPA) and Lighthouse Naugatuck, LLC (f/k/a Naugatuck Avenue Storage LLC); comment Date Dec 17, 2025

26
Nov
Canal CIP-IROL (Schedule 17) Section 205 Cost Recovery Filing

Canal files corrected Schedule 17; comment deadline Dec 17, 2025

25
Nov
PBOP Collections Report (Eversource)

FERC accept collections report, eff. Dec 8, 2025

24
Nov
Facilities (Distrigas) Support Agreement Cancellation - NSTAR/NGrid

FERC accepts cancellation, eff. Sep 30, 2025

21
Nov
CIP-IROL (Schedule 17) Cost Recovery Schedule Filing: FPL Wyman

FPL Wyman  requests FERC acceptance of a proposed rate schedule to allow it to begin the recovery period for certain Interconnection Reliability Operating Limits Critical Infrastructure Protection costs (“CIP-IROL Costs”) under Schedule 17 of the ISO-NE Tariff.  FPL Wyman stated that the rate schedule will provide interested parties notice of its intent to recover CIP-IROL Costs for its facility designated as an IROL-Critical Facility, and an order accepting the rate schedule will provide an effective date after which associated costs incurred can be recovered following completion of the process contemplated by Schedule 17 and a subsequent Section 205 filing identifying the specific costs to be recovered.

21
Nov
ANOPR: Interconnection of Large Loads to the Interstate Transmission System
RM26-4

ANOPR Comments filed by: 

21
Nov
ICR-Related Values and HQICCs – Annual Reconfiguration Auctions

ISO-NE and NEPOOL jointly file ICR-Related Values and HQICCs for 2026/27 ARA3 and 2027/28 ARA2

20
Nov
2025 OE Staff Enforcement Report

FERC Staff issues 2025 Enforcement Report

20
Nov
NOPR: Duty of Candor

FERC withdraws Duty of Candor NOPR and terminates rulemaking proceeding

20
Nov
ISO-NE FERC Form 3-Q

ISO-NE submits its 2025 Q3 FERC 3Q

20
Nov
Proposed Policy Statement: Waiver of Tariff Requirements

FERC withdraws Proposed Policy Statement and terminates this proceeding, finding (i) insufficient support on the record for the Proposed Policy Statement and (ii) that the issues discussed in the Proposed Policy Statement are, in general, better considered on a case-by-case basis. 

The FERC encouraged regulated entities to adopt tariff revisions that: (i) allow the entities to cure good-faith errors themselves within a discrete period of time without the need for a Commission waiver, and (2) provide advanced notice in the tariff that specific provisions may be waived by an order of the Commission (to help avoid conflicts with the filed rate doctrine and rule against retroactive ratemaking, which the FERC said had prevented it from granting some waiver requests that may have yielded more equitable outcomes).

19
Nov
Membership

ISO-NE submits notice of Phillip 66’s Nov 17, 2025 suspension from the ISO-NE Markets

18
Nov
Capital Projects Report - 2025 Q3

FEC accepts 2025 Q3 Capital Projects Report, eff. Oct 1, 2025

17
Nov
PSNH X-178 Powerline Rebuild Asset Condition Project Complaint

Individual Complainants (Kristina Pastoriza and Ruth Ward) request that the FERC conduct an objective expert third party investigation of the Eversource X-178 project (an asset condition project to rebuild the 49-mile line that runs from Beebe River to Whitefield, passing through the White Mountain National Forest).

17
Nov
Wholesale Distribution Tariff - Versant (II)

Versant files a revised Wholesale Distribution Tariff for Electric Energy Delivery to Energy Storage Systems, responding to the concerns expressed by the FERC in its order rejecting an earlier proposed WDT in ER25-2500

14
Nov
203 Application: CPower / NRG

FERC authorizes a proposed transaction pursuant to which NRG will indirectly acquire the membership interests in Enerwise Global Technologies, LLC d/b/a CPower (CPower), making NRG and CPower Related Persons.

14
Nov
CIP IROL (Schedule 17) Cost Recovery Filing: Canal Marketing

Canal requests recovery of $1,075,392 in CIP-IROL Costs incurred between Apr 1, 2024 and Mar 31, 2025; comment deadline Dec 5, 2025

12
Nov
BP Phantom Load Compaint

FERC grants an extension of time, to on or before Dec 12, 2025, for the filing of answers, interventions, comments, and protests to the Complaint

10
Nov
07
Nov
ANOPR: Interconnection of Large Loads to the Interstate Transmission System
RM26-4

FERC extends the date for submitting initial comments on the proposed ANOPR to and including Nov 21, 2025; reply comments due Dec 5, 2025

06
Nov
Order 898 Compliance Revisions

PTO AC submits for filing proposed revisions to the formula rate template (“Formula Rate”) contained in Appendix A to Attachment F of the ISO-NE OATT and to Appendix D to Attachment F
of the ISO-NE OATT in response to the requirements of FERC Order 898

06
Nov
ANOPR: Interconnection of Large Loads to the Interstate Transmission System

NESCOE supports Org. of MISO States (OMS) request for a 2-week extension of time, until
Nov 28, to submit initial comments