FERC grants RENEW’s Network Upgrades O&M Cost Allocation Complaint

FERC grants RENEW’s Complaint, directing ISO-NE and the PTOs to submit a compliance filing on or before Feb 18, 2025, (i) removing from the Tariff any provisions allowing the assignment of Network Upgrade O&M costs to Interconnection Customers; and (ii) revising the Formula Rate Protocols definition of “Interested Party” to include, but not be limited to customers under the Tariff, state utility regulatory commissions, consumer advocacy agencies, and state attorneys general.  These revisions shall be in effect prospectively, from the date of this order (Dec 19, 2024).  A more detailed summary by NEPOOL counsel was distributed to and posted on the website for the Transmission Committee.  