Mar 21, 2024 – NOPR Reactive Power Comp within the Standard Power Factor Range
Date:
Mar 21, 2024
Proceeding Type:
NOPR: Reactive Power Compensation
Docket:
RM22-2
Brief Description:

FERC proposes to revise (i) the pro forma OATT’s Schedule 2 to prohibit transmission providers from including in their transmission rates any charges associated with a generating facility’s supply of reactive power within the standard power factor range; and, accordingly, (ii) to remove from the pro forma LGIA and pro forma SGIA the requirement that a transmission provider pay an interconnection customer for reactive power within the standard power factor range if the transmission provider pays its own or affiliated generators for the same service, so that transmission providers would be required to pay an interconnection customer for reactive power only when the transmission provider asks the interconnection customer to operate its facility outside the standard power factor range set forth in its interconnection agreement.