Date:
Jul 16, 2024Proceeding Type:
RENEW Network Upgrades & O&M Cost Allocation ComplaintDocket:
EL23-16Brief Description:
RENEW submits Supplemental Affidavits as further evidence in support of its Dec 13, 2022 Complaint; requests that the FERC issue an order on an expedited basis determining that Schedules 11 and 21 of the ISO-NE OATT are unjust and unreasonable to the extent they permit transmission owners to directly assign to Interconnection Customers O&M costs associated with Network Upgrades constructed to facilitate a generator interconnection.