Dec 19, 2024 – Allco PP5 Complaint
Date:
Dec 19, 2024
Proceeding Type:
Allco PP-5 Complaint
Docket:
EL25-43
Brief Description:

Allco files a complaint asking the FERC to find (i) that PP-5’s procedures are unjust and unreasonable and unduly discriminatory and/or preferential in violation of section 206 of the FPA, and (2) that ISO-NE has violated the FPA by forcing on State jurisdictional interconnections, such as Allco’s, the requirement to pay for transmission level interconnection studies, to pay for PSCAD models in connection with such studies, and by causing the local distribution utility to delay executing State jurisdictional generator interconnection agreements (particularly for Allco’s 2 MW Winsted solar energy project).