Aug 16, 2021
Date:
Aug 16, 2021
Proceeding Type:
Interconnection Study Agreement: NSTAR/Servistar
Docket:
ER21-2696
Brief Description:

NSTAR files agreement in connection with proposed interconnection of Servistar’s 150 MW data center facility to Eversource’s 1293 and 1302 115 kV transmission lines