Oct 18, 2022 Order accepting Schedule 21-NEP: Narragansett/ Pawtucket Power Decomm. CRA
Date:
Oct 18, 2022
Proceeding Type:
Schedule 21-NEP: Narragansett/ Pawtucket Power Decomm. CRA
Docket:
ER21-2732
Brief Description:

FERC accepts a Decommissioning Cost Reimbursement Agreement (CRA) between Narragansett Electric and Pawtucket Power Associates LP (Pawtucket), eff. Jul 26, 2022.  The Decommissioning CRA facilitates the performance of certain work that Pawtucket has requested Narragansett undertake to support the decommissioning of certain interconnection facilities and related equipment for Pawtucket’s 69 MW Rhode Island generating facility that was completely retired on Jun 1, 2022. 